Project Facts
  • Remote project location.
  • Limited site access for equipment, materials and deliveries.
  • Bed rock conditions were encountered and rock blasting was required.
  • Specialized divers and equipment were required to accomplish the lake side portion of the work.
  • Value Engineering was required.
 
 



















  Project Portrait

The Lake Vermillion project included the installation of an HDPE water service line, from a submerged intake structure to a land side pre-fabricated pump house. The water service line was installed at the bottom of the lake, out approximately 2000 feet from the southern shoreline.

This installation required the use of commercial scuba divers and several pieces of support equipment. This project required diversion of the water line beneath federally protected vegetation at the shoreline.


Slide Rail Trailer/Pump House Installation